Project Details:
The site is located off Westbrook Close, Chapel en le frith alongside the existing Watercourse. The Banking areas followed the Watercourse through an existing Parkland area.
The work comprised the installation of Rock armour along a stretch of banking 30m long and including Coir Matting pegged into position. Timber Post and Rail fencing was also installed adjacent for Health and safety reasons.
All material was double handled from the existing Compound area, through the existing densely populated estate using dumpers and a Bankman.