Project Details:
The site is located within Mapperley Reservoir, Derbyshire.
The work comprised the raising and levelling of the existing Reservoir Wave wall for a length of 100m.
The existing Stone copings were drilled and dowelled with Stainless steel dowels and then a Concrete capping cast upon the existing wall.
Work was carried out using a Pontoon located on the main Reservoir.